A full 300 RT chiller isolation package costs about $470 FOB China — mounts, inertia base, flexible connectors, pipe hangers and restraints — and bills $2,800–4,200 once it is installed in a US mechanical room. The hardware is rarely the problem. Rigging, housekeeping pads, pipe rework and commissioning eat five to eight times more than the springs do.

Below is the actual line-by-line on a 300 RT (1,055 kW) water-cooled screw chiller, 3,500 kg operating weight on four points, priced FOB Ningbo in 2026 by the HeZheng engineering team. Use it to sanity-check a contractor's package price, or to build your own budget before the tender.

Vibration Damper

1. What Is Actually Inside a Chiller Isolation Package?

Five items, and only one of them is the mount: equipment springs, inertia base, flexible pipe connectors, pipe hanger isolation and restraint.

Priced at 100-piece quantities, 25 mm deflection unless stated:

 

Line

Spec

Qty

Unit FOB

Extended

Equipment mounts

1,000 kg rated spring, 25 mm

4

$14

$56

Isolation pads

Neoprene, 6 mm, under each mount

4

$1.00

$4

Inertia base

Fabricated steel, 2,500×1,200×200, unfilled

1

$180

$180

Flexible pipe connectors

DN150 (6") rubber, flanged

2

$38

$76

Pipe hanger isolation

Spring hanger, 75–1,250 kg, 50 mm

8

$7

$56

Seismic restraint kit

4-point, cable + bracket

1 set

$95

$95

Total, FOB Ningbo

 

 

 

$467

 

That is $1.56 per ton of cooling capacity. Across water-cooled chillers from 150 to 600 RT, a complete package lands between $1.20 and $2.00 per ton — so a $3,500 quote for a 300 RT machine is not a pricing error, it is a different scope.

What each line actually does, and where the cheap versions fail:

  • **Equipment mounts ($56).** Four units at roughly 875 kg each sit in the 800–2,000 kg band. A **[Vibration Damping Base](https://www.hezhengglobal.com/vibration-damper/68772259.html)** at this rating carries a bonded pad under a welded housing, which is what keeps 60 Hz motor noise out of the slab. Substituting a rubber block here saves $40 and loses everything below 15 Hz.
  • Inertia base ($180). Steel frame, unfilled, 2,500×1,200 mm. It adds mass and rigidity so the four springs work as one system instead of four independent ones. On a slab-on-grade floor with 300 mm of concrete, you can often skip it — that is the single biggest saving in the package, and the one most often skipped for the wrong reason.
  • Flexible connectors ($76). Two DN150 units, one per chilled-water header. Without them the pipe becomes a sound bridge and the springs are doing nothing. This is the cheapest line in the table and the most frequently omitted.
  • Pipe hanger isolation ($56). Eight spring hangers on the first 6–10 m of pipe each side, at 3 m spacing. A Vibration Damper at 50 mm deflection and 75–1,250 kg covers DN100–DN200 risers and is adjustable after installation, which matters because pipe loads are estimated, not weighed.
  • Restraint ($95). Cable-and-bracket kit for four points. Required in seismic zones, optional elsewhere, and never substitutable with rigid blocking. A chiller restrained with angle iron is a chiller with no isolation at all.

One selection trap worth pricing for: nameplate shipping weight is not operating weight. A 300 RT screw chiller gains 400–600 kg once the evaporator and condenser are charged, and a package sized on the shipping figure ends up 12–17% under-rated — exactly the light-loading condition that raises natural frequency. HeZheng sizes on operating weight plus 10%.

✅ Bottom line: Nearly 30% of a package price sits in the two lines contractors most often cut — flexible connectors and pipe hanger isolation.


2. Why Does the Installed Price Land at 6–9× the Hardware?

Because the springs are 15% of the job. The other 85% is rigging, concrete, pipe rework and proving the thing actually works.

Same 300 RT job, priced through to a running machine in a US mechanical room:

  • Factory hardware, FOB Ningbo: $467
  • Freight, LCL 1.2 m³, insurance: $90–140
  • Duty and customs clearance: $30–55
  • Distributor margin, 1.8–2.4×: $1,050–1,500
  • Rigging and crane, half day: $400–900
  • Housekeeping pad, 3,500×1,500, 150 mm: $300–600
  • Pipe rework and re-alignment after mounts go in: $500–1,500
  • Commissioning vibration survey, before and after: $500–1,500
  • Installed total: $2,800–4,200

Two observations follow. First, the hardware is never where a project goes over budget — the rigging and pipe rework are, and both scale with how late the isolation package is ordered. Ordering after the chiller lands adds a second rigging day at $400–900 and usually forces a field-fabricated base. Second, a 20% saving on the mounts is worth $11 on a $3,500 job, while skipping the flexible connectors saves $76 and costs you the whole isolation objective.

Where the package genuinely scales up: above 500 RT, chillers usually arrive with six or eight mounting points instead of four, and per-point loads pass 2,000 kg. A 9,000 kg machine at 2,000–4,500 kg per point needs a Vibration Isolator with a covered spring cage and lateral stops, and the mount line alone triples even though the tonnage only doubles.

Scope disputes are also where packages quietly double. On most US jobs the mechanical contractor carries pipe hangers inside the piping scope while the isolation vendor carries equipment mounts — so the eight hangers on the chiller riser get counted twice, or not at all. Write the split into the quote: mounts and base from the isolation supplier, hangers and connectors inside the piping package, restraints wherever seismic applies.

Practical rules for budgeting the package:

  • Budget $1.20–2.00 per ton of cooling capacity for hardware — below that, something is missing from the scope.
  • Always include flexible connectors and the first 10 m of pipe hanger isolation; these two lines decide whether the package works.
  • Price the inertia base separately and decide it on floor construction, not on habit.
  • Add 15% for restraints only if the project is in a seismic zone with a stamped requirement.
  • Order the package with the chiller, not after it lands — rigging a second time costs more than the mounts.

✅ Bottom line: Judge a package on scope completeness, not unit price; the hardware is 15% of what the project actually spends.


FAQ

Q: Is $3,500 for a 300 RT package reasonable?

A: For installed, engineered scope in a US mechanical room, yes — that sits inside the $2,800–4,200 range. For hardware only, no: FOB content is roughly $470 and landed stock is $550–700.

Q: Can I buy the mounts only and source the rest locally?

A: Usually yes, and it often saves 20–30%. Keep the restraint kit matched to the mount, though — mixing brands is where inspection failures happen. HeZheng quotes mounts, bases and hanger isolation as one schedule so the load ratings stay consistent.

Q: Do you supply custom base frames and OEM packages?

A: Yes. HeZheng fabricates inertia bases and frames to drawing, supplies mixed containers with mounts, pads and hangers, and offers OEM marking on wholesale orders. Custom drawings quote in 24 hours; standard bulk production runs 15 working days off-season.


Send the Chiller Schedule, Get a Priced Package

Send the chiller model, operating weight, mounting points and pipe sizes, and HeZheng will return a line-by-line package price — mounts, base, connectors, hangers, restraints — within 12 hours, with the per-ton number already calculated so you can compare it against your contractor's scope.

 

Email:[email protected]

Mobile: +86 13681606005

Website:www.hezhengglobal.com